Saturday, February 28, 2015

23 FEB 15: Page 20-5 step 9 (right), pg 20-6 step 3 (right): 2 hours
Finished deburring and dimpling the right wing skin and bottom rib flanges; riveted the nutplates on the right wing skin access holes – no pics.

24, 26, 27 FEB 15: Page 20-5 steps 11-12: 7 hours
My friend, and fellow RV builder, Mike came over several nights this week and helped me finish riveting the left bottom wing skin.  He has worked at Gulfstream for 17 years and is a master on the bucking bar.  He chose to do the bucking – which I was very thankful for.   All of these rivets are bucked blindly and some at a far reach.  Due to his experience we ended up only needing to drill out a few rivets and finished with no dings in the skin.  After the first evening – finished the inboard skin and the aft spar on the outboard skin:
All finished with the left wing after the 3rd evening:

25 FEB 15: Fuselage Delivery
Well, I’m just past the 1 year mark and tonight the fuselage was delivered – it was a huge crate – about 550 pounds.  Just as the truck showed up it started pouring.  Oh well, for the size of the crate, the driver pretty easily unloaded it and had it in the garage in no time.  Pretty big!
Most of the space is used by the cabin top.  A lot of fiberglass work in my future:

28 FEB 15: Finish-filing pitot mast, page 21-5 step 5 (right redo): 1.25 hours
Did some finish filing of the pitot mast and did the final install.  Looks pretty nice:
I had Van’s throw the replacement aileron skins into the fuse crate – if you remember, I dimpled and installed the stiffeners onto the incorrect side of the right aileron skins.  Deburred the stiffener holes and edges.  Priming to follow.